Reference library

NCT requirements register (synthetic)

152 requirements · 48 checked by deterministic rules, the others by discipline agents · 25 documents in the document register. Synthetic, modelled on the kind of design basis, specifications and procedures a CO2 transport project uses; standards are cited by number only.

152 shown
IDRequirementSourceApplies toPriorityCheck
NCT-R-DCC-001Document number format
Every project document shall carry a document number of the form NCT-<discipline>-<type>-<nnnn>, where discipline is a three-letter code and type a two- or three-letter code.
NCT-DCC-PR-0004 Rev A
§3.1
DS, SP, PID, LL, IL, CA, PR, DW, ITPMediumdocnumber_format
NCT-R-DCC-002Valid revision code
Revisions shall be identified by a single capital letter (A, B, C ...) before 'Issued for Construction' and by a number (0, 1, 2 ...) from 'Issued for Construction' onwards. Combined codes such as 'C1' are not allowed.
NCT-DCC-PR-0004 Rev A
§3.4
DS, SP, PID, LL, IL, CA, PR, DW, ITPLowrevision_format
NCT-R-DCC-003References to current revisions
Where a document references another project document by revision, the referenced revision shall be the current revision in the document register; references to superseded revisions are not allowed.
NCT-DCC-PR-0004 Rev A
§4.2
DS, SP, PID, LL, IL, CA, PR, DW, ITPMediumrefs_current
NCT-R-DCC-004Referenced documents exist
Every project document number referenced in a document shall exist in the project document register.
NCT-DCC-PR-0004 Rev A
§4.3
DS, SP, PID, LL, IL, CA, PR, DW, ITPLowrefs_exist
NCT-R-DCC-005SI units
Values shall be stated in SI units (bar(g), degC, mm, m, kg). Imperial units (psi, degF, ft, lb) are not allowed, except nominal pipe sizes in inches.
NCT-DCC-PR-0004 Rev A
§5.1
DS, SP, PID, LL, IL, CA, PR, DW, ITPLowsi_units
NCT-R-DCC-006Document language
Documents shall be written in English. Procedures executed by Dutch site personnel may be written in Dutch.
NCT-DCC-PR-0004 Rev A
§5.3
SP, PR, CA, ITPLowagent
NCT-R-DCC-007Revision history
Each document shall contain a revision history stating revision, date, description and author.
NCT-DCC-PR-0004 Rev A
§6.1
SP, PR, CA, ITPLowsection_required
NCT-R-DCC-008Title block complete
Every drawing shall have a title block with project, document number, title, revision, date, status, drawn, checked, approved, scale and sheet filled in.
NCT-DCC-SP-0005 Rev A
§2.2
PID, DWMediumtitleblock_complete
NCT-R-DCC-009Status code on drawings
The status in the title block shall be one of IFR (issued for review), IFA (issued for approval) or IFC (issued for construction).
NCT-DCC-SP-0005 Rev A
§2.4
PID, DWLowtitleblock_value
NCT-R-DCC-010CAD layer standard
CAD drawings shall use the project layer names (e.g. PROCESS, INSTR, VALVES, TEXT, TITLEBLOCK, DIMENSIONS); layer 0 shall not carry content.
NCT-DCC-SP-0005 Rev A
§3.1
PID, DWLowlayers_standard
NCT-R-DCC-011Page numbering
Pages shall be numbered 'Page x of y' (or 'Pagina x van y').
NCT-DCC-PR-0004 Rev A
§5.4
SP, PR, CA, ITPLowagent
NCT-R-DCC-012Document status stated
The issue purpose (IFR, IFA, IFC) shall be stated on the cover page or title block.
NCT-DCC-PR-0004 Rev A
§6.3
DS, SP, PID, LL, IL, CA, PR, DW, ITPLowagent
NCT-R-DCC-013Hold list
Open items in a document shall be listed in a hold list with the action owner; 'TBD' without a hold is not allowed.
NCT-DCC-PR-0004 Rev A
§7.1
SP, PRLowagent
NCT-R-DCC-014Reference list
Each specification, calculation, procedure and ITP shall contain a list of referenced documents and standards.
NCT-DCC-PR-0004 Rev A
§7.2
SP, CA, PR, ITPLowsection_required
NCT-R-PRC-001Design pressure
The design pressure of the compressor discharge system and the trunkline is 150 barg. Documents shall use this value.
NCT-PRC-DB-0001 Rev D
§4.1
DS, SP, PID, LL, CA, PRHighfield_eq
NCT-R-PRC-002Maximum allowable operating pressure
The maximum allowable operating pressure (MAOP) is 140 barg.
NCT-PRC-DB-0001 Rev D
§4.1
DS, SP, LL, CAMediumfield_eq
NCT-R-PRC-003Minimum design temperature (general)
The minimum design temperature is -20 degC for buried and above-ground process piping.
NCT-PRC-DB-0001 Rev D
§4.2
DS, SP, LL, CAHighagent
NCT-R-PRC-004Minimum design temperature for depressurisation
Vent, blowdown and relief lines and all valves that can see depressurisation of dense-phase CO2 shall be designed for a minimum design temperature of -46 degC.
NCT-PRC-DB-0001 Rev D
§4.2
SP, LLHightable_rule
NCT-R-PRC-005Maximum design temperature
The maximum design temperature is 50 degC downstream of the after-cooler.
NCT-PRC-DB-0001 Rev D
§4.2
DS, SP, LL, CAMediumagent
NCT-R-PRC-006CO2 specification - purity
Equipment shall be suitable for CO2 with a purity of at least 95 mol%.
NCT-PRC-DB-0001 Rev D
§3.2
SP, CA, PRMediumagent
NCT-R-PRC-007CO2 specification - water content
The design shall assume a maximum water content of 50 ppmv in the transported CO2; free water shall never be present in operation.
NCT-PRC-DB-0001 Rev D
§3.3
SP, CA, PRHighagent
NCT-R-PRC-008CO2 specification - impurities
Materials shall be compatible with the impurity limits of the design basis (O2 <= 10 ppmv, H2S <= 5 ppmv, SOx and NOx <= 10 ppmv each).
NCT-PRC-DB-0001 Rev D
§3.3
SPMediumagent
NCT-R-PRC-009Overpressure protection
Every section that can be blocked in shall be protected against overpressure by a relief device or an instrumented protection system.
NCT-PRC-DB-0001 Rev D
§4.4
PIDMediumagent
NCT-R-PRC-010Dense-phase operation
The trunkline is operated in dense phase; the operating envelope shall stay above 80 barg in normal operation.
NCT-PRC-DB-0001 Rev D
§4.5
PID, SPMediumagent
NCT-R-PRC-011Pig launcher
The compressor discharge shall include a pig launcher suitable for intelligent pigging of the trunkline.
NCT-PRC-DB-0001 Rev D
§5.1
PIDMediumagent
NCT-R-PRC-012Piggability
All valves in the trunkline shall be full bore to allow pigging.
NCT-PRC-DB-0001 Rev D
§5.2
PID, SPMediumagent
NCT-R-PRC-013Emergency shutdown valves
Emergency shutdown valves (XV) shall be provided at the compressor discharge and at the landfall valve station.
NCT-PRC-DB-0001 Rev D
§5.3
PIDHighagent
NCT-R-PRC-014Blowdown
Each isolatable section shall have a blowdown valve routed to the vent stack.
NCT-PRC-DB-0001 Rev D
§5.4
PIDMediumagent
NCT-R-PRC-015Design pressure on P&ID notes
Design conditions stated on P&IDs shall match the design basis (150 barg / -46 to +50 degC for the discharge and trunkline).
NCT-PRC-DB-0001 Rev D
§4.1
PIDHighfield_eq
NCT-R-PRC-016Insulation for personnel protection
Surfaces hotter than 60 degC or colder than -10 degC within reach shall have personnel protection.
NCT-PRC-DB-0001 Rev D
§4.6
PID, LLLowagent
NCT-R-PRC-017Design life
The design life of the transport system is 30 years.
NCT-PRC-DB-0001 Rev D
§6.1
CAMediumagent
NCT-R-PRC-018Ambient conditions
Outdoor equipment shall be designed for ambient temperatures from -20 degC to +35 degC and a coastal (C5-M) atmosphere.
NCT-PRC-DB-0001 Rev D
§6.2
SP, DSLowagent
NCT-R-PRC-019Line numbering on P&IDs
Every process line on a P&ID shall carry a line number of the form <size>"-<fluid>-<nnnn>-<piping class>.
NCT-PRC-DB-0001 Rev D
§4.7
PIDMediumpattern_all
NCT-R-PRC-020Line list consistency
Every line number shown on a P&ID shall appear in the line list.
NCT-PRC-DB-0001 Rev D
§4.7
PIDMediumlines_in_linelist
NCT-R-PRC-021Line list design pressure
In the line list, all CO2 lines in the discharge and trunkline system shall have a design pressure of 150 barg.
NCT-PRC-DB-0001 Rev D
§4.8
LLMediumtable_rule
NCT-R-PRC-022Line list test pressure
The line list shall state a hydrotest pressure of at least 1.5 times the design pressure for every CO2 line.
NCT-PRC-DB-0001 Rev D
§4.8
LLLowtable_rule
NCT-R-PRC-023Specification breaks
Piping class breaks shall be shown on the P&ID.
NCT-PRC-DB-0001 Rev D
§4.9
PIDLowagent
NCT-R-PRC-024Cold-temperature embrittlement
Measures against brittle fracture during depressurisation shall be described for all components that can reach -46 degC.
NCT-PRC-DB-0001 Rev D
§7.1
SP, PRMediumagent
NCT-R-PRC-025Running ductile fracture
The line pipe design shall address running ductile fracture arrest for dense-phase CO2.
NCT-PRC-DB-0001 Rev D
§7.2
CAMediumagent
NCT-R-PIP-001Allowed line pipe grades
Line pipe shall be ISO 3183 PSL2 grade L415ME or L450ME. Other grades require an approved deviation.
NCT-PIP-SP-0003 Rev B
§3.1
CA, SP, DSMediumfield_allowed
NCT-R-PIP-002Corrosion allowance
A corrosion allowance of 3.0 mm shall be applied to all carbon-steel piping and line pipe in CO2 service.
NCT-PIP-SP-0003 Rev B
§3.2
CA, LL, SPHighfield_min
NCT-R-PIP-003Design factor
The design factor for line pipe shall not exceed 0.72.
NCT-PIP-SP-0003 Rev B
§3.3
CAHighfield_max
NCT-R-PIP-004Wall thickness formula
Wall thickness shall be calculated with the hoop-stress (Barlow) formula t = P*D/(2*SMYS*F) plus corrosion allowance and fabrication tolerance.
NCT-PIP-SP-0003 Rev B
§3.4
CAMediumagent
NCT-R-PIP-005Fabrication tolerance
A negative wall thickness fabrication tolerance of 12.5% shall be considered unless the mill guarantees less.
NCT-PIP-SP-0003 Rev B
§3.5
CAMediumagent
NCT-R-PIP-006Calculation inputs traceable
All calculation inputs shall be traceable to a referenced project document and revision.
NCT-PIP-SP-0003 Rev B
§3.6
CALowagent
NCT-R-PIP-007Piping class for 150 barg
CO2 lines with 150 barg design pressure shall use piping class B9C (ASME Class 900, carbon steel low-temperature).
NCT-PIP-SP-0003 Rev B
§4.1
LL, PIDMediumtable_rule
NCT-R-PIP-008Piping class for vent lines
Vent and blowdown lines shall use low-temperature piping class L9C.
NCT-PIP-SP-0003 Rev B
§4.1
LLMediumtable_rule
NCT-R-PIP-009Insulation code
Every line in the line list shall carry an insulation code (N = none, PP = personnel protection, H = heat conservation).
NCT-PIP-SP-0003 Rev B
§4.3
LLLowtable_rule
NCT-R-PIP-010Girth weld NDT extent
100% of the girth welds of the trunkline shall be examined by automated ultrasonic testing (AUT) or radiography.
NCT-PIP-SP-0003 Rev B
§5.1
ITP, PRHighfield_min
NCT-R-PIP-011Positive material identification
PMI shall be performed on all alloy materials and on 10% of low-temperature carbon-steel components.
NCT-PIP-SP-0003 Rev B
§5.2
ITPMediumagent
NCT-R-PIP-012Coating holiday detection
External coating shall be 100% holiday tested before lowering-in.
NCT-PIP-SP-0003 Rev B
§5.3
ITPMediumagent
NCT-R-PIP-013Welding procedure qualification
Welding procedures shall be qualified including Charpy impact testing at -46 degC.
NCT-PIP-SP-0003 Rev B
§5.4
ITP, PRMediumagent
NCT-R-PIP-014Minimum wall thickness
The selected nominal wall thickness of the 32-inch trunkline shall not be less than 15.9 mm.
NCT-PIP-SP-0003 Rev B
§6.1
CAMediumfield_min
NCT-R-PIP-015Outside diameter
The outside diameter of the 32-inch trunkline is 813 mm.
NCT-PIP-SP-0003 Rev B
§6.2
CALowfield_eq
NCT-R-PIP-016Cathodic protection
Buried line pipe shall be protected by external coating and impressed-current cathodic protection.
NCT-PIP-SP-0003 Rev B
§6.3
CAMediumagent
NCT-R-PIP-017Toughness requirements
Line pipe shall meet Charpy toughness requirements for fracture arrest as defined in the line pipe specification.
NCT-PIP-SP-0003 Rev B
§6.4
CA, SPLowagent
NCT-R-PIP-018Line list completeness
The line list shall state for every line: size, fluid, from, to, piping class, design pressure, minimum and maximum design temperature, corrosion allowance, insulation and test pressure.
NCT-PIP-SP-0003 Rev B
§7.1
LLLowagent
NCT-R-PIP-019Line reference to P&ID
Every line in the line list shall reference the P&ID on which it is shown.
NCT-PIP-SP-0003 Rev B
§7.2
LL, PIDLowagent
NCT-R-PIP-020Corrosion allowance in line list
The line list shall show a corrosion allowance of 3.0 mm for every carbon-steel CO2 line.
NCT-PIP-SP-0003 Rev B
§3.2
LLHightable_rule
NCT-R-VLV-001Body material for low-temperature service
Valve bodies exposed to -46 degC shall be ASTM A350 LF2 Class 1 (forged) or ASTM A352 LCC (cast). ASTM A105 and A216 WCB are not allowed.
NCT-MEC-SP-0007 Rev B
§4.1
SP, DSHighfield_allowed
NCT-R-VLV-002Elastomers resistant to rapid gas decompression
Elastomeric seals in CO2 service shall be qualified for rapid gas decompression (RGD) according to ISO 23936-2 or NORSOK M-710; standard nitrile (NBR) is not allowed.
NCT-MEC-SP-0007 Rev B
§4.2
SP, DSHighagent
NCT-R-VLV-003Fire-safe design
Trunkline ball valves shall be fire-safe certified to ISO 10497 or API 607. The specification shall contain a fire-safe section.
NCT-MEC-SP-0007 Rev B
§4.3
SPMediumsection_required
NCT-R-VLV-004Fugitive emission class
Valves shall meet ISO 15848-1 tightness class B (or better, class A).
NCT-MEC-SP-0007 Rev B
§4.4
SPMediumfield_allowed
NCT-R-VLV-005Pressure class
Valves in the 150 barg system shall be ASME B16.34 / B16.5 Class 900.
NCT-MEC-SP-0007 Rev B
§4.5
SP, PID, DSHighfield_allowed
NCT-R-VLV-006Full bore
Trunkline valves shall be full bore and piggable.
NCT-MEC-SP-0007 Rev B
§4.6
SPMediumagent
NCT-R-VLV-007Double block and bleed
Trunkline ball valves shall provide double block and bleed (DBB) functionality.
NCT-MEC-SP-0007 Rev B
§4.7
SPMediumagent
NCT-R-VLV-008Seat material
Seats shall be metal or PEEK; PTFE seats are not allowed in CO2 service above 100 barg.
NCT-MEC-SP-0007 Rev B
§4.8
SPMediumagent
NCT-R-VLV-009Shell and seat test
Each valve shall be shell tested at 1.5 times and seat tested at 1.1 times the rated pressure, plus a low-pressure gas seat test.
NCT-MEC-SP-0007 Rev B
§5.1
SPMediumagent
NCT-R-VLV-010Low-temperature test
One valve per size and class shall be cryogenically tested at -46 degC with seat leakage measurement.
NCT-MEC-SP-0007 Rev B
§5.2
SPMediumagent
NCT-R-VLV-011Actuator fail-safe position
Shutdown valve actuators shall be spring-return, fail-closed.
NCT-MEC-SP-0007 Rev B
§6.1
SPMediumagent
NCT-R-VLV-012Actuator sizing margin
Actuators shall be sized with a safety factor of at least 1.5 on the maximum valve torque.
NCT-MEC-SP-0007 Rev B
§6.2
SPLowagent
NCT-R-VLV-013Stroke time
Shutdown valves shall close within 30 seconds.
NCT-MEC-SP-0007 Rev B
§6.3
SPMediumagent
NCT-R-VLV-014External coating
Above-ground valves shall be coated for a C5-M environment per ISO 12944.
NCT-MEC-SP-0007 Rev B
§7.1
SPLowagent
NCT-R-VLV-015Marking
Valves shall be marked with tag number, size, class, body material and flow direction where applicable.
NCT-MEC-SP-0007 Rev B
§7.2
SPLowagent
NCT-R-VLV-016Material certificates
Pressure-retaining parts shall have EN 10204 type 3.1 material certificates.
NCT-MEC-SP-0007 Rev B
§8.1
SPMediumagent
NCT-R-VLV-017Vendor documentation
The vendor shall supply general arrangement drawings, a cross-section with parts list, test certificates and an installation and maintenance manual.
NCT-MEC-SP-0007 Rev B
§8.2
SPLowagent
NCT-R-VLV-018Stem design
Valve stems shall be anti-blow-out design.
NCT-MEC-SP-0007 Rev B
§4.9
SPMediumagent
NCT-R-VLV-019Bolting
Bolting for low-temperature valves shall be ASTM A320 L7 with A194 grade 7 nuts.
NCT-MEC-SP-0007 Rev B
§4.10
SPLowagent
NCT-R-VLV-020Design temperature of valves
Valves shall be designed for -46 degC to +50 degC.
NCT-MEC-SP-0007 Rev B
§4.11
SP, DSMediumagent
NCT-R-VLV-021Cavity relief
Ball valves shall have automatic body cavity relief.
NCT-MEC-SP-0007 Rev B
§4.12
SPMediumagent
NCT-R-VLV-022Spare parts
The vendor shall propose commissioning spares and two years of operating spares.
NCT-MEC-SP-0007 Rev B
§9.1
SPLowagent
NCT-R-INS-001Calibrated range covers design pressure
Pressure transmitters on the 150 barg system shall have a calibrated range whose upper value is at least 1.1 times the design pressure (165 barg).
NCT-INS-SP-0002 Rev 1
§3.1
DS, ILHighrange_upper_min
NCT-R-INS-002Ingress protection
Field instruments shall have ingress protection of at least IP66.
NCT-INS-SP-0002 Rev 1
§3.2
DSMediumfield_min
NCT-R-INS-003Hazardous-area certification
Instruments in the compressor area shall be certified for Zone 1, gas group IIB, temperature class T4 (Ex d or Ex ia).
NCT-INS-SP-0002 Rev 1
§3.3
DS, ILHighfield_allowed
NCT-R-INS-004Output signal
Transmitters shall have a 4-20 mA output with HART.
NCT-INS-SP-0002 Rev 1
§3.4
DS, ILMediumagent
NCT-R-INS-005Wetted materials
Wetted parts of pressure instruments shall be AISI 316L as a minimum.
NCT-INS-SP-0002 Rev 1
§3.5
DSMediumagent
NCT-R-INS-006Accuracy
Pressure transmitter reference accuracy shall be 0.075% of span or better.
NCT-INS-SP-0002 Rev 1
§3.6
DSLowagent
NCT-R-INS-007Process connection
Process connection shall be 1/2-inch NPT female via a double block and bleed manifold.
NCT-INS-SP-0002 Rev 1
§3.7
DSLowagent
NCT-R-INS-008Electrical connection
Electrical connection shall be M20 x 1.5.
NCT-INS-SP-0002 Rev 1
§3.8
DSLowagent
NCT-R-INS-009Instrument tag format
Instrument and valve tags shall have the form <unit>-<function>-<nnnn>, e.g. 110-PT-1011 (three-digit unit, two- to four-letter function, four-digit loop number).
NCT-INS-SP-0002 Rev 1
§4.1
PID, IL, DSMediumpattern_all
NCT-R-INS-010P&ID instruments in instrument index
Every instrument tag shown on a P&ID shall appear in the instrument index.
NCT-INS-SP-0002 Rev 1
§4.2
PIDMediumtags_in_index
NCT-R-INS-011Unique tags
Each tag shall appear only once in the instrument index.
NCT-INS-SP-0002 Rev 1
§4.3
ILLowno_duplicates
NCT-R-INS-012P&ID reference in index
Every instrument in the index shall reference an existing P&ID.
NCT-INS-SP-0002 Rev 1
§4.4
ILLowtable_refs_exist
NCT-R-INS-013Datasheet tags in index
Every tag on an instrument datasheet shall appear in the instrument index.
NCT-INS-SP-0002 Rev 1
§4.5
DSLowtags_in_index
NCT-R-INS-014Calibration certificate
Each transmitter shall be delivered with a factory calibration certificate traceable to national standards.
NCT-INS-SP-0002 Rev 1
§5.1
DSMediumagent
NCT-R-INS-015Display
Transmitters shall have a local LCD display in engineering units.
NCT-INS-SP-0002 Rev 1
§5.2
DSLowagent
NCT-R-INS-016Housing material
Housings shall be stainless steel or copper-free aluminium with a C5-M coating.
NCT-INS-SP-0002 Rev 1
§5.3
DSLowagent
NCT-R-INS-017Overpressure limit
The sensor overpressure limit shall be at least 1.5 times the design pressure.
NCT-INS-SP-0002 Rev 1
§5.4
DSLowagent
NCT-R-INS-018Diagnostics
Transmitters in SIS service shall have diagnostic coverage reported in the SIL certificate.
NCT-INS-SP-0002 Rev 1
§5.5
DSMediumagent
NCT-R-INS-019Index completeness
The instrument index shall state for every tag: service, type, range, signal, SIL, P&ID and hazardous-area certification.
NCT-INS-SP-0002 Rev 1
§6.1
ILLowagent
NCT-R-INS-020Instrument line symbols
Instrument signal lines shall follow ISA 5.1 symbols.
NCT-INS-SP-0002 Rev 1
§6.2
PIDLowagent
NCT-R-INS-021Pressure measurement redundancy
SIS pressure measurements shall be 2oo3 voted transmitters.
NCT-INS-SP-0002 Rev 1
§6.3
PIDMediumagent
NCT-R-INS-022Manufacturer and model stated
The datasheet shall state manufacturer and model number for each instrument.
NCT-INS-SP-0002 Rev 1
§6.4
DSLowagent
NCT-R-INS-023Damping
Transmitter damping shall be adjustable from 0 to 60 seconds.
NCT-INS-SP-0002 Rev 1
§6.5
DSLowagent
NCT-R-SIS-001SIL capability for SIS transmitters
Transmitters in safety-instrumented functions shall be certified SIL 2 capable (IEC 61508) as a minimum.
NCT-INS-SP-0011 Rev A
§3.1
DS, ILHighsil_min
NCT-R-SIS-002Proof test interval
The datasheet shall state the proof test interval assumed in the SIL certificate (12 months maximum).
NCT-INS-SP-0011 Rev A
§3.2
DSMediumagent
NCT-R-SIS-003SIS tagging on P&ID
Safety-instrumented loops shall be identified on the P&ID with the SIF number.
NCT-INS-SP-0011 Rev A
§3.3
PIDMediumagent
NCT-R-SIS-004Shutdown valve SIL
Shutdown valves in safety functions shall have a SIL 2 capability certificate for the valve and actuator assembly.
NCT-INS-SP-0011 Rev A
§3.4
SPMediumagent
NCT-R-SIS-005Partial stroke testing
Shutdown valves shall support partial stroke testing.
NCT-INS-SP-0011 Rev A
§3.5
SPMediumagent
NCT-R-AFP-001Testdruk / test pressure
The strength test pressure shall be at least 1.5 times the design pressure (225 barg).
NCT-MEC-SP-0009 Rev A
§2.1
PRHighfield_min
NCT-R-AFP-002Houdtijd / hold time
The hold time of the combined strength and leak test shall be at least 24 hours.
NCT-MEC-SP-0009 Rev A
§2.2
PRHighfield_min
NCT-R-AFP-003Testmedium / test medium
The test medium shall be filtered fresh water (filter 50 micrometre or finer) with a corrosion inhibitor; seawater is not allowed.
NCT-MEC-SP-0009 Rev A
§2.3
PRHighagent
NCT-R-AFP-004Drogen / drying
After dewatering, the line shall be dried to a water dew point of -40 degC or lower at atmospheric pressure before CO2 is introduced. The procedure shall contain a drying section.
NCT-MEC-SP-0009 Rev A
§3.1
PRHighsection_required
NCT-R-AFP-005Dauwpuntmeting / dew point measurement
The dew point shall be measured at the far end of the section with a calibrated hygrometer and recorded.
NCT-MEC-SP-0009 Rev A
§3.2
PRMediumagent
NCT-R-AFP-006Kalibratie drukschrijver / recorder calibration
Pressure and temperature recorders and dead-weight testers shall have been calibrated within the last 6 months.
NCT-MEC-SP-0009 Rev A
§4.1
PRMediumfield_max
NCT-R-AFP-007Temperatuurmeting / temperature recording
Pipe wall and ambient temperature shall be recorded continuously during the hold period.
NCT-MEC-SP-0009 Rev A
§4.2
PRMediumagent
NCT-R-AFP-008Acceptatiecriterium / acceptance criterion
The test is accepted when pressure variations are fully explained by temperature effects and no leaks are found.
NCT-MEC-SP-0009 Rev A
§4.3
PRMediumagent
NCT-R-AFP-009Veiligheidszone / safety zone
A safety zone shall be established and marked around the test section during pressurisation.
NCT-MEC-SP-0009 Rev A
§4.4
PRMediumagent
NCT-R-AFP-010Opdruksnelheid / pressurisation rate
The pressurisation rate above 50% of the test pressure shall not exceed 1 bar per minute.
NCT-MEC-SP-0009 Rev A
§4.5
PRLowagent
NCT-R-AFP-011Afvoer testwater / test water disposal
Test water shall be disposed of under a permit; inhibitor concentration shall be recorded.
NCT-MEC-SP-0009 Rev A
§5.1
PRMediumagent
NCT-R-AFP-012Testrapport / test report
The test report shall contain the recorder charts, calibration certificates, test log and signatures of contractor and owner.
NCT-MEC-SP-0009 Rev A
§5.2
PRMediumagent
NCT-R-AFP-013Getuige opdrachtgever / owner witness
The strength and leak test is a hold point witnessed by the owner's inspector.
NCT-MEC-SP-0009 Rev A
§5.3
PR, ITPHighagent
NCT-R-AFP-014Ontluchten / venting
The section shall be vented at high points to remove air before pressurisation.
NCT-MEC-SP-0009 Rev A
§2.4
PRMediumagent
NCT-R-AFP-015Testsecties / test sections
Test section limits shall be defined with their elevation profile so that the test pressure at the highest point is not below the minimum.
NCT-MEC-SP-0009 Rev A
§2.5
PRMediumagent
NCT-R-AFP-016Ontwateren met pigs / dewatering by pigs
Dewatering shall be done with at least two foam or bi-directional pigs driven by dry air or nitrogen.
NCT-MEC-SP-0009 Rev A
§3.3
PRMediumagent
NCT-R-HSE-001Vent stack distance to site boundary
The vent stack shall be at least 60 m from the site boundary.
NCT-HSE-SP-0006 Rev A
§3.1
DWHighdimension_min
NCT-R-HSE-002Control room separation
The control room shall be at least 30 m from the compressor building.
NCT-HSE-SP-0006 Rev A
§3.2
DWMediumdimension_min
NCT-R-HSE-003Two escape routes
Each building and process area shall have at least two escape routes in different directions.
NCT-HSE-SP-0006 Rev A
§3.3
DWMediumagent
NCT-R-HSE-004CO2 gas detection
Fixed CO2 gas detection shall be provided in the compressor building and at low points where CO2 can accumulate.
NCT-HSE-SP-0006 Rev A
§3.4
DW, PIDMediumagent
NCT-R-HSE-005Wind direction indicators
At least two wind socks shall be visible from all process areas.
NCT-HSE-SP-0006 Rev A
§3.5
DWLowagent
NCT-R-HSE-006Assembly points
Primary and secondary assembly points shall be shown on the plot plan, upwind of the vent stack for the prevailing wind.
NCT-HSE-SP-0006 Rev A
§3.6
DWMediumagent
NCT-R-HSE-007North arrow and prevailing wind
Plot plans shall show a north arrow and the prevailing wind direction.
NCT-HSE-SP-0006 Rev A
§3.7
DWLowagent
NCT-R-HSE-008Emergency vehicle access
Emergency vehicles shall have access to every process area from two sides.
NCT-HSE-SP-0006 Rev A
§3.8
DWMediumagent
NCT-R-HSE-009Asphyxiation hazard
Procedures and specifications for CO2 systems shall address the asphyxiation hazard of CO2 releases.
NCT-HSE-SP-0006 Rev A
§4.1
SP, PRMediumagent
NCT-R-HSE-010Toolbox meeting
Site procedures shall require a toolbox meeting before high-pressure work.
NCT-HSE-SP-0006 Rev A
§4.2
PRLowagent
NCT-R-HSE-011Vent stack height
The vent stack shall be at least 30 m high (exit above grade).
NCT-HSE-SP-0006 Rev A
§3.9
DWMediumagent
NCT-R-HSE-012Fence and gates
The site shall be fenced with at least two gates.
NCT-HSE-SP-0006 Rev A
§3.10
DWLowagent
NCT-R-CIV-001Drawing scale stated
Plot plans shall be drawn to a stated scale (e.g. 1:500 or 1:1000); 'NTS' is not allowed for layouts.
NCT-HSE-SP-0006 Rev A
§5.1
DWLowtitleblock_value
NCT-R-CIV-002Dimensions in metres
Layout dimensions shall be in metres and the unit shall be stated on the drawing.
NCT-HSE-SP-0006 Rev A
§5.2
DWLowagent
NCT-R-CIV-003Site roads
An access road shall run along the site with connection to the public road.
NCT-HSE-SP-0006 Rev A
§5.3
DWMediumagent
NCT-R-CIV-004Substation location
The electrical substation shall be located outside hazardous areas.
NCT-HSE-SP-0006 Rev A
§5.4
DWLowagent
NCT-R-CIV-005Vent stack routing
Blowdown and vent lines shall be routed to the vent stack shown on the plot plan.
NCT-HSE-SP-0006 Rev A
§5.5
DW, PIDMediumagent
NCT-R-QAC-001Owner hold point for pressure test
The pressure test of the pipeline shall be an owner hold point (H) in the ITP.
NCT-QAC-SP-0008 Rev A
§3.1
ITPHighagent
NCT-R-QAC-002ITP references procedures
Every ITP activity shall reference the governing procedure or specification by number.
NCT-QAC-SP-0008 Rev A
§3.2
ITPMediumagent
NCT-R-QAC-003Acceptance criteria
Every ITP activity shall state its acceptance criteria.
NCT-QAC-SP-0008 Rev A
§3.3
ITPMediumagent
NCT-R-QAC-004Records
Every ITP activity shall state the verifying record (certificate, report or checklist).
NCT-QAC-SP-0008 Rev A
§3.4
ITPLowagent
NCT-R-QAC-005Material receipt inspection
The ITP shall include receipt inspection of line pipe including certificate review.
NCT-QAC-SP-0008 Rev A
§3.5
ITPMediumagent
NCT-R-QAC-006Welder qualification
Welder qualification shall be verified before production welding (review point).
NCT-QAC-SP-0008 Rev A
§3.6
ITPMediumagent
NCT-R-QAC-007Drying verification
The ITP shall include verification of drying to the specified dew point as an owner hold point.
NCT-QAC-SP-0008 Rev A
§3.7
ITPMediumagent
NCT-R-QAC-008As-built survey
The ITP shall include an as-built survey of the pipeline route.
NCT-QAC-SP-0008 Rev A
§3.8
ITPLowagent
NCT-R-QAC-009Intervention codes
Intervention codes shall be H (hold), W (witness), R (review) and S (surveillance) for contractor and owner.
NCT-QAC-SP-0008 Rev A
§3.9
ITPLowagent
NCT-R-QAC-010Coating repair
Coating repairs shall be inspected and holiday tested.
NCT-QAC-SP-0008 Rev A
§3.10
ITPMediumagent

Document register

used to check cross-references and superseded revisions

NCT-PRC-DB-0001DDesign Basis - CO2 transport systemcurrent
NCT-PRC-DB-0001CDesign Basis - CO2 transport systemsuperseded
NCT-INS-SP-00021Project specification - Field instrumentationcurrent
NCT-PIP-SP-0003BPiping material specification and line pipecurrent
NCT-DCC-PR-0004ADocument numbering and revision procedurecurrent
NCT-DCC-SP-0005ACAD and drawing standardcurrent
NCT-HSE-SP-0006ALayout and safety distances specificationcurrent
NCT-MEC-SP-0007BPipeline valve specificationcurrent
NCT-QAC-SP-0008AQuality requirements for construction (ITP)current
NCT-MEC-SP-0009AProjectspecificatie afpersen en drogen (NL)current
NCT-QAC-PR-0910AHydrotest quality procedurecurrent
NCT-INS-SP-0011AFunctional safety (SIS) requirementscurrent
NCT-INS-DS-0101AInstrument datasheet - Pressure transmitters, compressor dischargecurrent (under review)
NCT-MEC-SP-0201AVendor technical specification - Trunkline ball valvescurrent (under review)
NCT-PRC-PID-0301AP&ID - Compressor discharge and pig launchercurrent (under review)
NCT-PRC-PID-0302AP&ID - Landfall valve stationcurrent (under review)
NCT-PIP-LL-0401ALine list - Compressor station and trunklinecurrent (under review)
NCT-INS-IL-0501AInstrument index - Compressor station and landfallcurrent (under review)
NCT-PIP-CA-0601AWall thickness calculation - 32-inch trunklinecurrent (under review)
NCT-MEC-PR-0701AAfpersprocedure onshore leidingsectie (hydrotest procedure)current (under review)
NCT-CIV-DW-0801APlot plan - Compressor stationcurrent (under review)
NCT-QAC-ITP-0901AInspection and test plan - Pipeline constructioncurrent (under review)
NCT-INS-DS-0102AInstrument datasheet (not in this package)current
NCT-INS-DS-0103AInstrument datasheet (not in this package)current
NCT-INS-DS-0104AInstrument datasheet (not in this package)current